|
Project Booklet -
Polish Home for a
New Century |
|
|
|
(booklet updated in
November 2007) |
The Polish Home has been a
cultural center and the hub
of the Polish community of
Seattle and the Puget Sound
area since 1919. The
building itself was
constructed in 1902. It was
remodeled and renovated
several times, notably in
late 1960s and over the last
decade. Among other things,
the bar and the lower hall
have been remodeled and the
floor and other elements
upstairs have been
renovated. In 2004, new
noise reducing windows were
installed and the Ladies
Auxiliary remodeled the
kitchen.
Despite all the positive
changes, the overall state
of the building is not
satisfactory. The building
started as a dance hall and
in fact was one of the most
popular dance halls in
Seattle in the 1930s. Today,
it has changed its
character. It is home to
multiple organizations
important to the Polish
community and a scene of
many cultural events.
However, it is no longer
functional for new and
upcoming needs. First, we
need an elevator to improve
access not only for the
disabled and the elderly,
but also for many functions
held at the second floor.
Second, space is needed for
another meeting room, for
secure exhibitions, or for a
small theater with Polish TV
or film club meetings.
Finally, the building also
needs several technical
improvements. It does not
conform to modern building
codes and has an old
electrical wiring and sewer
lines. The stage upstairs
requires complete remodeling
that should also include
changes to the backstage
area, emergency exit and
stairs. Lastly, parking wais
a perennial cause of
complaints, but that has
been already improved as
part of the current project.
It is firm belief of the
Committee that improving the
functionality of the
building, and thus
facilitating organization of
events, is essential to
attracting more people to
the Polish Home. In so
doing, it is our goal to
develop the Polish Home into
a vibrant hub for a new
century.
In light of these issues,
Polish Home Association (PHA)
initiated an expansion and
remodeling program that
should bring the Polish Home
into the 21st
century. Polish Home
Foundation (PHF), being a
public charity with the
501(c)(3) tax exempt status
is leading the fundraising
campaign to finance the
extensions. This is the
project that is described in
this booklet.
Project overview
There are many improvements
that the Polish Home
requires. Actual
improvements will be
selected based on the
available finances.
The Master Plan
The Master Plan has been
discussed for some time in
our community; it has been
adopted in 2001and related
architectural plans
presented in 2003. The
community feedback was taken
in 2004 & 2006. The Plan was
approved by the PHA with the
following phases:
Phase I
Extension of the front
of the building towards the
street
-
An entrance foyer with a
new wide staircase, an
elevator from the street
level to the ground
floor and upper floors,
-
Second floor with
library storage room as
well a room serving as a
library reading lounge,
a secure exhibition
hall, a meeting room,
and small film theater,
-
Third floor that would
be left empty at this
stage.
Changes to the parking
lot
·
Removing of the shed next to
the manager house and
increasing the number of
stalls from 28 to 42
·
New fence and landscaping on
the north side of the
property
We focus on Phase I only -
Phase II of the Master Plan
will be priced & implemented
once the extension is built
and financed appropriately.
Phase II
Consolidation and
internal improvements
include the following:
-
Recovering space used by
the current stairs as
new storage rooms,
finishing interior
changes,
-
Finishing an apartment
on the third floor,
-
A new air conditioning
system. It would be
mounted on the top of
the extension but would
service the whole
building.
The Master Plan also
included rebuilding the
stage upstairs; however the
current plan is to do it
independent of the Expansion
Project.
Pricing for the whole
project depends on the
number of elements
implemented. Please turn to
the Fundraising chapter for
estimates.
Progress as of October 2007
The Phase I of the project
has been in implementation
since 2005. The effort is
coordinated by two volunteer
committees. The PH
Association Building
Commission governs the
technical aspects of the
project, while the PH
Foundation Fundraising
Committee coordinates
fundraising. Contacts to the
committees are listed on the
back cover of this booklet.
Master Permit received from
the City in 2006
The PH Building Commission
received the Master Permit
for the project in 2006. The
Permit is an initial
permission for the project.
To start the actual
construction, a Building
Permit is needed.
Extensions to the parking
lot in 2006-2007
As per the Master Permit
negotiations with the City,
the parking lot changes were
scheduled first. That part
of the project was done in
2006 & 2007 for about
$32,000. The work included
-
Removing of the shed
next to the manager
house
-
Increasing the number of
stalls from 28 to 42
-
Asphalt paving for the
new stalls and widening
of driveways
-
New fence and
landscaping on the north
side of the property
Plans completed, Building
Permit applied for in 2007
The construction plans were
completed in the summer 2007
and formally signed in the
fall 2007. The Building
Commission is filing for the
Building Permit with the
City. The plan review by the
City should last about 4 to
6 months and may result in
further modifications to the
plans for the project.
General contractor chosen,
cost estimates done
In June, 2007, the Polish
Home Association chose
Shinstine Assoc. of
Puyallup, WA, as the general
contractor for the project.
Based on bids from
subcontractors, Shinstine
Assoc. presented costs
estimates to the Polish Home
in the fall of 2007. This
removes the guesswork from
the previous estimates and
presents a clear target for
fundraising. The goal is to
start the construction in
the summer of 2008 (please
see a cost discussion in the
financing chapter of the
booklet).
Changes to the project
Since 2005, several changes
have been introduced to the
project by the Architect,
Mr. Roy Koczarski, based on
negotiations with the City,
input from the Building
Commission, feedback from
Polish Home user groups and
from community comments. The
current design is described
in this booklet and
displayed in the Polish Home
lobby.
Vigorous fundraising
campaign – over $330,000 and
counting
The Polish Home Fundraising
Committee started a vigorous
fundraising campaign in May
2005 seeking not only direct
donations to the project but
also multi-year giving
pledges (spanning two, three
or more years). Besides cash
pledges the Committee also
accepts professional service
pledges, when donors offer
to render them free of cost.
As of October 2007, over
150 families, organizations
and individuals pledged over
$330,000 to the project;
this includes about $75,000
in professional service
pledges. So far over
$180,000 has been received
in cash donations as well as
in income from fundraising
events and interest.
Grants
A significant achievement of
the campaign is securing a
$10,000 grant from the
Seattle Foundation.
The Foundation is committed
to building healthy
communities by supporting
community oriented projects
in the greater Seattle area.
We are really grateful to
the Seattle Foundation for
this support. The Committee
identified several other
Foundations to apply to and
we hope to secure other
grants for the project.
Plans for 2007-2008
Reinforcing the building
foundations
As a follow up to
professional inspections
done in 2006 & 2007, the
building foundations will be
reinforced before the new
construction starts. This
work is currently planned
for the fall of 2007 and
early 2008.
More fundraising,
construction tentative in
2008
The fundraising campaign
shall continue to run in
2007 and 2008. Our goal is
to collect enough pledges
(if not actual donations)
that the construction can
start in the summer of 2008.
Starting construction is
contingent both on having
sufficient funding and on
receiving the Building
Permit by late spring of
2008.

Fig.1. Polish Home site
plan: new addition to the
building (planned)
and expansion of the parking
lot (already done)
Project Details
The main goal of the project
is to construct an extension
to the building with
additional rooms for better
functionality, with a
working hydraulic elevator
and new stairs. The
additional rooms, hallway,
and stairs would be finished
to the extent required to
obtain the occupancy permit
for the building from the
City.
The site plan on the
previous page shows that the
proposed extension is an
addition to the current
building structure. After
the extension is built, some
remodeling changes in the
old structure are also
possible, but this is not
part of the Phase I effort.

Fig.2. West elevation
The extension adds about 868
sq. ft at the ground floor
and 1,200 sq ft at the
second floor. Currently both
floors of the building have
4,630 sq ft for a total of
9,260 sq ft. The third floor
would add about 1,200 sq ft.
Once the extension is being
built, the cost of adding
the third floor is quite
low; thus substantial
additional space can be
gained inexpensively for
future use. Overall, the
extension would add about
3,268 sq ft to the current
9,260 sq ft.
The plans shown in this
booklet are close to final.
The basic plan is set (the
addition with new rooms,
elevator & stairs); however,
some details may still
change. The City had already
imposed a set of project
restrictions pertaining to
height, width and depth
(street clearance) of the
addition in the Master
Permit. The City can impose
new requirements in the
Building Permit that is
needed to start the actual
construction.

Fig.3.Partial elevation from
the parking

Fig.4.Partial elevation from
south (Madison)
The entrance foyer is at the
sidewalk (street) level with
no steps. Inside, there are
few steps down from the
entrance foyer to the
current ground level
hallway. Disabled access is
possible as visitors can
turn left and access the
elevator at the same level.
The elevator can be entered
from two sides with
passengers going from the
street level down to the
current first floor (lower
lobby) or up to the upper
floors. On the right there
is a new, wider staircase
with lower steps and an
intermediate landing half
way up to the second floor.
The manager’s office is
moved.

Pillars supporting a
cantilevered second floor
make for a shaded (arcaded)
access to the building and a
bigger area upstairs. The
view on the next page shows
the second floor of the
addition with the new
stairs, elevator exit, and
the library room that would
also serve as a meeting room
and an exhibition room. This
room could also be used as a
small theater for a film
club or for watching Polish
TV through satellite. It
would also be used by the
Polish School.
The space used by the old
stairs and passageway
downstairs will be
remodeled. Downstairs, a
teachers’ room and school
storage will be created.
Upstairs, there will be new
storage rooms for the piano,
tables and chairs that now
are kept in the concert hall
upstairs. This solves the
problem of the big metal
carts cluttering floor space
during big events.

Below is a plan of the third
floor with the elevator
access. The space on this
floor would be left unused
during Phase I, thus cutting
on the construction costs of
the addition. The space
would be converted into an
apartment for the building
manager later.

Please note that building an
apartment does not mean any
changes to the current
manager building as
discussed initially. The
current manager building
will not be demolished;
instead it can be rented
when the apartment is done.
Construction costs
How much does it cost?
How much do we need to
construct the extension to
the building and how much to
execute on all the elements
of the Master Plan?
The construction cost is
about 500,000
for the addition with the 3rd
floor left empty (as per the
current plan following Phase
I of the Master Plan); after
adding 10% reserve for
contingencies and the WA
state sales tax, the
total cost is about
$600,000. This
estimate is based on actual
construction bids as of fall
2007 but it might change
depending on when the actual
construction starts.
The Master Plan includes
Phase II with several other
elements to do such as
completing the manager
apartment, remodeling the
current structure to better
use available space, adding
a new air-conditioning to
the whole building etc.
Costs for these elements are
not included in the above
estimate as it is too early
to define the scope of that
work.
We expect the bulk of
financing to come from the
cash generated by cash
pledges, grants and
fundraising events. There
are no plans to take a
construction loan, unless it
can be secured by the
pledges. We have also
received significant service
pledges for the project.
These include professional
services such as making
architectural plans,
structural calculations,
electrical work, roofing,
siding, painting and
carpentry.
Fundraising
Striving for wide community
support
The fundraising campaign we
run is a wide grass-root
campaign aimed at contacting
over 1000 families and
individuals related to the
Polish Home, starting with
PHA members. As of October
2007, we received pledges
from over 150 families,
organizations and
individuals, so there is
still a way to go. We ask
every family to donate about
$500-$1,000 to the campaign
to collect enough funds.
However, every amount helps.
Many pledges are for $50,
$100 or $200 and we
certainly invite more
pledges like that! For many
people it is easier to
pledge smaller yearly
donations over span of 2 or
3 years, and such pledges
are welcome.
Keeping the community
informed
The campaign publishes
regular reports about the
project in the local
bilingual quarterly
published by PHA,
Nasz Dom, and on
the PHF website. Also,
community wide letters are
sent about once a year.
Fundraising beyond local
Polish community
We are expanding the
campaign to go beyond the
Polish community of the
Puget Sound. We plan to
appeal both to local general
public and the Polish
communities and
organizations across the
United States.
Grants
In March 2007, the project
received a $10,000 grant
from the Seattle Foundation
from its program for
building healthy
communities. We plan to
apply for more grants for
the project. We welcome help
and suggestions for grant
application writing and
targeting.
Fundraising events and other
income
Special events are organized
by the Polish community to
generate income for the
project.
Pierogi Fest of
2006 and 2007 turned out to
be a very popular event and
we plan to continue it in
the future. Other plans for
2007/2008 season include a
Biesiada concert.
Also, finances for the
project have been invested
in CDs, thus generating
interest income for the
project.
Recognizing donors
The Fundraising Committee
publishes the donor list in
the local quarterly
Nasz Dom and on
the PHF website. The list of
donors is presented in
sections corresponding to
donation value ranges with
donor names listed
alphabetically without
specific values. The ranges
are as follows: $25,000 or
more, $10,000-$24,999,
$5000–$9999, $2000-$4999,
$1000-$1999, $500-$999,
$200-$499, $100-$199 and up
to $99. Upon completion of
the construction, the Polish
Home will mount a special
board (or boards) to honor
project donors and
volunteers.
Naming opportunities
Naming opportunities are
special ways of honoring
donors who have contributed
exceptional amounts. The
opportunities for this
campaign include naming the
library, the concert hall
upstairs and the elevator.
Bricks for the project
The campaign will make some
other opportunities
available later. In
particular, the Committee
also plans to make space
available for special
plaques or bricks once the
construction plans are
finalized.
Gift plans
Many donors would like to
spread their contributions
over time for personal
reasons or due to matching
gift plan limitations. We
embrace any schedule that is
convenient to the supporters
of the project. If you like
to give in smaller
installments over a longer
period of time, the table
below can help with planning
such contributions.
Spreading your gifts over 2
years
|
Gift plan |
Pledge |
First install. |
Annually |
Quarterly |
Monthly |
Daily amount |
|
Partner |
25,000 |
2,500 |
11,250 |
2,812.5 |
937.5 |
30.82 |
|
Champion |
10,000 |
1,000 |
4,500 |
1,125 |
375 |
12.32 |
|
Guardian |
5,000 |
500 |
2,250 |
562.5 |
187.5 |
6.16 |
|
Patron |
2,000 |
200 |
900 |
225 |
75 |
2.47 |
|
Builder |
1,000 |
100 |
450 |
112.5 |
37.5 |
1.23 |
|
Provider |
500 |
50 |
225 |
56.25 |
18.75 |
0.62 |
|
Supporter |
200 |
20 |
90 |
22.5 |
7.5 |
0.25 |
|
Friend |
100 |
10 |
45 |
11.25 |
3.75 |
0.12 |
|
Helper |
50 |
5 |
22.5 |
5.63 |
1.88 |
0.06 |
Please note that other gift
plans (shorter or longer
than two years) are also
possible.
Matching Gift Programs
When considering a pledge,
please ask your employer if
there is a gift matching
plan available that could be
used to increase your
effective donation. At the
print time the following
Puget Sound companies are
known to offer matching gift
programs to their employees:
Boeing, Microsoft, Oracle,
Safeco and Starbucks.
FAQ
updated
Nov, 2007